Invoice Deposits

Many construction invoices are paid in stages -- a deposit on signing, a progress payment at milestones, and a final payment on handover. Cornerstone lets you track these staged payments as deposits within a single parent invoice, so your budget rollups reflect what has actually been paid out at any point in time rather than waiting for the full invoice to settle.

What is a Deposit?​

A deposit is a partial payment recorded against an invoice. Each deposit has its own amount, due date, status, and (optionally) a description. The amounts you record as deposits eat into the invoice total -- whatever is left after the deposits is the final payment, which uses the parent invoice's status.

The math is simple:

  • Σ deposits + final payment = invoice total
  • Deposit total must not exceed the invoice total. The form refuses to save if it would.

Each deposit is one of three statuses, mirroring the parent invoice status model:

StatusMeaning
PendingDeposit is scheduled (or due) but not yet paid
PaidDeposit has been paid to the vendor
ClaimedDeposit has been claimed back from / reimbursed by a financing source

Allowed transitions: pending → paid, paid → claimed, and the reverse path (claimed → paid → pending) to correct mistakes.

Adding a Deposit​

Open any invoice's detail page. The Deposits section appears below the invoice header and shows:

  • The current deposit count
  • A list of existing deposits with amount, due date, status badge, and description
  • An Add deposit button

Click Add deposit to open the form:

FieldDescription
AmountDeposit amount. Must be positive and must keep the running total at or below the invoice total.
Due dateWhen the deposit is owed -- used for the schedule and for the overdue indicator.
StatusPending (default), Paid, or Claimed.
Paid dateShown when status is Paid or Claimed -- defaults to today, change if it was paid earlier.
Claimed dateShown when status is Claimed -- defaults to today, change if it was claimed earlier.
DescriptionOptional free-text label (e.g., "30% on contract signing", "Milestone payment after framing").

Save the form to record the deposit. The Deposits list re-renders with the new entry, and the budget rollups across linked work items and household items update immediately to reflect the contribution.

Editing and Deleting Deposits​

Each deposit row has an overflow menu with Edit and Delete.

  • Edit opens the same form with the deposit's current values. Status changes are restricted to the allowed transitions above; for example, you cannot move directly from Pending to Claimed -- mark it Paid first.
  • Delete removes the deposit. If the deposit is Paid or Claimed, the modal warns you that deleting will reduce the paid/claimed amount rolled up against budget lines.

You can also mark a deposit as Paid or Claimed without editing it: the mark paid and mark claimed quick actions in the overflow menu open a small confirmation modal where you can set the paid or claimed date.

If you mark a deposit Paid or Claimed by mistake, use the same menu to revert it -- the action is allowed and shows a transient error banner if the revert fails (for example, due to a network glitch).

How Deposits Affect Budget Rollups​

Deposits change the timing of cost recognition, not the total. Cornerstone splits each invoice across its deposits proportionally for every budget line the invoice is linked to:

  • actualCost (total) -- the full itemized amount counts toward the budget line regardless of deposit status. Even a Pending deposit contributes to actualCost, because the invoice as a whole is a committed cost.
  • actualCostPaid -- only the portion of the itemized amount covered by Paid or Claimed deposits, plus the residual final payment if the parent invoice is itself Paid or Claimed.
  • actualCostClaimed -- only the portion covered by Claimed deposits, plus the residual final payment if the parent invoice is Claimed.

In practice: if you have a €10,000 invoice linked to a budget line at its full €10,000, and you record a €3,000 Paid deposit while the invoice itself is still Pending, the budget line shows €10,000 actual cost but only €3,000 paid. The remaining €7,000 stays as a pending obligation until either the parent invoice transitions to Paid or you add more Paid deposits to cover it.

The status breakdown summary on each invoice list and the per-source budget overview both use this deposit-aware math, so paid and claimed amounts always reflect real cash flow rather than waiting for the entire invoice to settle.

Quotations and Deposits​

Quotation invoices accept deposits the same way as regular invoices, but quotation amounts are treated with a ±5% projection margin in the budget overview (ADR-029). Deposits against a Quotation invoice contribute to actualCost but only contribute to actualCostPaid / actualCostClaimed if their own status is Paid or Claimed.

Cascade Behaviour​

Deposits are owned by the parent invoice. Deleting an invoice cascades and removes all its deposits in the same transaction -- you do not need to delete deposits one by one before deleting the invoice.

Next Steps​

  • Invoices & Vendors -- creating invoices and linking them to budget lines
  • Budget Overview -- how deposit-aware totals roll up across categories and sources
  • Subsidies -- subsidy calculations also use itemized amounts and respect deposit status